 "pcon24cd": "E14001243",
 "name": "Gainsborough",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 583.1,
  "stuck_mw_int": 583,
  "stuck_sites": 8,
  "homes_equivalent": 212000,
  "homes_vs_seat_households": 5.0,
  "stuck_mw_12m_cut": 1675.0,
  "consented_not_built_mw_any_age": 2176.2,
  "operational_mw": 47.8,
  "operational_homes_equivalent": 17000,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 1.8,
  "rank": 6,
  "tech_mix": {
   "solar": 583.1
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 12.2,
  "projects": [
   {
    "site_name": "Cottam Solar Project",
    "repd_ref_id": 10914,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 600.0,
    "homes_equivalent": 218000,
    "consented": "2024-09-05",
    "months_waiting": 22.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Gate Burton - Solar & Energy Storage Park",
    "repd_ref_id": 9809,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 531.0,
    "homes_equivalent": 193000,
    "consented": "2024-07-12",
    "months_waiting": 24.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Tillbridge Solar Farm, Hemswell - Solar Panels",
    "repd_ref_id": 12281,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 500.0,
    "homes_equivalent": 182000,
    "consented": "2025-10-14",
    "months_waiting": 9.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "West Burton Solar Project",
    "repd_ref_id": 10916,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 480.0,
    "homes_equivalent": 174000,
    "consented": "2025-01-24",
    "months_waiting": 18.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "The Old Airfield Solar Photovoltaic Farm",
    "repd_ref_id": 9575,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 49.9,
    "homes_equivalent": 18000,
    "consented": "2021-05-27",
    "months_waiting": 62.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Highgate Lane, Normanby-By-Spital - Solar Photovoltaic Farm",
    "repd_ref_id": 15113,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 11.0,
    "homes_equivalent": 4000,
    "consented": "2025-07-24",
    "months_waiting": 12.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Top Farm, Short Ferry Road - Solar PV Arrays",
    "repd_ref_id": 13519,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.9,
    "homes_equivalent": 300,
    "consented": null,
    "months_waiting": null,
    "status": "Under Construction"
   },
   {
    "site_name": "A Poucher & Sons, Lodge Farm - Solar Panels",
    "repd_ref_id": 15111,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.8,
    "homes_equivalent": 300,
    "consented": "2023-12-01",
    "months_waiting": 32.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Waddingham Grange, Kirton Road - Solar Panels",
    "repd_ref_id": 18551,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2025-05-30",
    "months_waiting": 14.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Gainsborough Educational Village, Sweyn Lane - Solar PV Panels",
    "repd_ref_id": 15160,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2023-12-21",
    "months_waiting": 31.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Hemswell Coldstore, Caenby Corner Estate - Solar Panels & Battery",
    "repd_ref_id": 20505,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2026-04-22",
    "months_waiting": 3.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "David Lloyd Leisure, Burton Waters - Solar PV Panels",
    "repd_ref_id": 14369,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2023-08-22",
    "months_waiting": 35.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Ping Europe Limited, Corringham Road - Solar Array",
    "repd_ref_id": 13344,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2023-03-29",
    "months_waiting": 40.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Barff Farm, Glentham - Solar Panels",
    "repd_ref_id": 17237,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2024-09-01",
    "months_waiting": 23.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "River Cottage, Scampton - Solar Panels",
    "repd_ref_id": 11360,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2022-07-15",
    "months_waiting": 48.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Harvest Pet Products Limited - Solar Panels",
    "repd_ref_id": 11610,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2022-08-01",
    "months_waiting": 48.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Grange Farm, Station Road -  Solar Panels",
    "repd_ref_id": 16823,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.1,
    "homes_equivalent": 100,
    "consented": "2024-09-24",
    "months_waiting": 22.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Gulham Fields Poultry Unit, Gulham Road - Solar Panels",
    "repd_ref_id": 18468,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2025-03-21",
    "months_waiting": 16.4,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.95,
  "seat_households": 42345,
  "seat_total_gbp": 3900000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 10.0,
  "building_mw": 0.0,
  "approved_mw": 20.2,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 66.0,
  "sites": [
   {
    "site_name": "Barfield Lane, Reepham - Battery Energy Storage System",
    "capacity_mw": 53.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 186000
   },
   {
    "site_name": "West Burton Solar Project",
    "capacity_mw": 20.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 70000
   },
   {
    "site_name": "Leverton Farm - Energy Barn",
    "capacity_mw": 10.0,
    "status": "operating",
    "year": null,
    "homes_while_discharging": 35000
   },
   {
    "site_name": "Marton Sewage Works, High Street - Battery Energy Storage",
    "capacity_mw": 10.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 35000
   },
   {
    "site_name": "Welton Gathering Centre, Sudbrooke - Battery Storage",
    "capacity_mw": 3.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 11000
   },
   {
    "site_name": "Burton Lane - Micro Energy Storage",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Cottam Solar Project",
   "repd_ref_id": 10914,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 600.0,
   "homes_equivalent": 218000,
   "status": "Awaiting Construction",
   "consented": "2024-09-05",
   "refused": null,
   "planning_authority": "The Planning Inspectorate - National Infrastructure",
   "planning_ref": "EN010133",
   "operator": "Island Green Power",
   "reason": {
    "reason": "connection_date",
    "label": "Cannot connect to the grid until 2029, 5 years after it was approved",
    "who": "the grid operator (NESO) and National Grid",
    "evidence": {
     "project": "Cottam Solar PV + BESS",
     "connection_date": "2029-09-01",
     "mw": 600.0,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2029",
   "tec": {
    "project": "Cottam Solar PV + BESS",
    "connection_date": "2029-09-01",
    "connection_year": 2029,
    "mw": 600.0,
    "stage": null,
    "who": "the grid operator (NESO) and National Grid",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Gate Burton - Solar & Energy Storage Park",
   "repd_ref_id": 9809,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 531.0,
   "homes_equivalent": 193000,
   "status": "Awaiting Construction",
   "consented": "2024-07-12",
   "refused": null,
   "planning_authority": "The Planning Inspectorate - National Infrastructure",
   "planning_ref": "EN010131",
   "operator": "Low Carbon",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-07-12",
     "years_since_consent": 2.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Tillbridge Solar Farm, Hemswell - Solar Panels",
   "repd_ref_id": 12281,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 500.0,
   "homes_equivalent": 182000,
   "status": "Awaiting Construction",
   "consented": "2025-10-14",
   "refused": null,
   "planning_authority": "The Planning Inspectorate - National Infrastructure",
   "planning_ref": "EN010142",
   "operator": "Tillbridge Solar Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-10-14",
     "years_since_consent": 0.8
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "West Burton Solar Project",
   "repd_ref_id": 10916,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 480.0,
   "homes_equivalent": 174000,
   "status": "Awaiting Construction",
   "consented": "2025-01-24",
   "refused": null,
   "planning_authority": "The Planning Inspectorate - National Infrastructure",
   "planning_ref": "EN010132",
   "operator": "Island Green Power",
   "reason": {
    "reason": "connection_date",
    "label": "Cannot connect to the grid until 2028, 3 years after it was approved",
    "who": "the grid operator (NESO) and National Grid",
    "evidence": {
     "project": "West Burton Solar Project",
     "connection_date": "2028-11-30",
     "mw": 480.0,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2028",
   "tec": {
    "project": "West Burton Solar Project",
    "connection_date": "2028-11-30",
    "connection_year": 2028,
    "mw": 480.0,
    "stage": null,
    "who": "the grid operator (NESO) and National Grid",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Barfield Lane, Reepham - Battery Energy Storage System",
   "repd_ref_id": 12600,
   "technology": "Battery",
   "capacity_mw": 53.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "147131",
   "operator": "Fiskerton Bess Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 2.9 years for a planning decision",
    "who": "West Lindsey Council",
    "evidence": {
     "submitted": "2023-09-01",
     "months_waiting": 35
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "The Old Airfield Solar Photovoltaic Farm",
   "repd_ref_id": 9575,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Awaiting Construction",
   "consented": "2021-05-27",
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "142117",
   "operator": "Grey Street Solar Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2021-05-27",
     "years_since_consent": 5.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Airfield Farm - Solar Array",
   "repd_ref_id": 9891,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "WL/2026/00180",
   "operator": "Engena Limited",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2026, still waiting for a decision",
    "who": "West Lindsey Council",
    "evidence": {
     "submitted": "2026-02-24",
     "months_waiting": 5
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Stow Park Farm, Stow Park - Solar Panels",
   "repd_ref_id": 14270,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 35.0,
   "homes_equivalent": 13000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "WL/2024/00395",
   "operator": "Luminous Energy Group",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 2.2 years for a planning decision",
    "who": "West Lindsey Council",
    "evidence": {
     "submitted": "2024-06-07",
     "months_waiting": 26
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "South Carlton - Solar Panels",
   "repd_ref_id": 19099,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 29.0,
   "homes_equivalent": 11000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "WL/2025/00737",
   "operator": "Enviromena",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 1.0 years for a planning decision",
    "who": "West Lindsey Council",
    "evidence": {
     "submitted": "2025-07-21",
     "months_waiting": 12
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "West Burton Solar Project",
   "repd_ref_id": 10917,
   "technology": "Battery",
   "capacity_mw": 20.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-01-24",
   "refused": null,
   "planning_authority": "The Planning Inspectorate - National Infrastructure",
   "planning_ref": "EN010132",
   "operator": "Island Green Power",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-01-24",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Highgate Lane, Normanby-By-Spital - Solar Photovoltaic Farm",
   "repd_ref_id": 15113,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 11.0,
   "homes_equivalent": 4000,
   "status": "Awaiting Construction",
   "consented": "2025-07-24",
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "WL/2024/00415",
   "operator": "Boultbee Brooks Renewables Walkford Moor Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-07-24",
     "years_since_consent": 1.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Marton Sewage Works, High Street - Battery Energy Storage",
   "repd_ref_id": 20514,
   "technology": "Battery",
   "capacity_mw": 10.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "WL/2026/00169",
   "operator": "Loire Capital Holdings Limited",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2026, still waiting for a decision",
    "who": "West Lindsey Council",
    "evidence": {
     "submitted": "2026-02-18",
     "months_waiting": 5
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Hemswell Biogas, Hemswell Cliff Industrial Estate - Anaerobic Digestion",
   "repd_ref_id": 13029,
   "technology": "Anaerobic Digestion",
   "capacity_mw": 6.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-06-04",
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "PL/0100/22",
   "operator": "A M Duguid & Son (BioteCH4)",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-06-04",
     "years_since_consent": 2.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Welton Gathering Centre, Sudbrooke - Battery Storage",
   "repd_ref_id": 11792,
   "technology": "Battery",
   "capacity_mw": 3.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lindsey",
   "planning_ref": "PL/0086/22",
   "operator": "Island Gas Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 4.0 years for a planning decision",
    "who": "West Lindsey Council",
    "evidence": {
     "submitted": "2022-07-21",
     "months_waiting": 48
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001476",
  "E14001336",
  "E14001128",
  "E14001462",
  "E14001343",
  "E14001375"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}