Mid Buckinghamshire
Mid Buckinghamshire has 136 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 49,000 homes. No wind farm here is paid to switch off. Almost every pound of that money goes to wind farms in Scotland, where there is not enough wire capacity to carry the power south. The cost is shared across every bill in Britain, so households here pay too: about £92 a year per household, £3.6m across the constituency's 39,109 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Whirlbush Farm, Kingsey - Solar Farm & Battery Storage | Solar Photovoltaics | 18,000 homes | 49.9 MW | 2022-03 | 4.4 yrs |
| Callie's Solar Farm | Solar Photovoltaics | 18,000 homes | 49.9 MW | 2022-11 | 3.7 yrs |
| Moat Farm - Solar Farm | Solar Photovoltaics | 8,700 homes | 24.1 MW | 2022-02 | 4.4 yrs |
| Bumpers Farm Phase 2 | Solar Photovoltaics | 4,400 homes | 12.0 MW | 2015-10 | 10.8 yrs |
| Haddenham Garden Centre, Stanbridge Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.4 MW | 2023-02 | 3.4 yrs |
Plus 5 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| East Claydon Substation, East Claydon Road - Energy Storage | 500 MW | in planning | could supply ≈1,752,000 homes |
| Bumpers Lane Solar Farm | 13 MW | could supply ≈47,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →