No.11 OF 650 · APPROVED, NOT BUILT MP: Alicia Kearns (Conservative) England

Rutland and Stamford

Rutland and Stamford has 379 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 138,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 39,908 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
379 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 138,000 homes — 3 times every household in this constituency. Approved at least two years ago; waiting on the grid, not on planning. That is 16.4× the renewable capacity actually running here.
6 projects · planning database (REPD), July 2026 · how we worked this out
£3.7m
is what the grid gap costs this constituency's 39,908 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 6 waiting projects · years since approval
Ranksborough Farm 28 MW
4.5 YRS
Morrison - Roof mounted solar panels 1 MW
4.2 YRS
Openfield, Colsterworth - Solar PV System 0 MW
4.0 YRS
Cherryholt Road - Solar Panels 0 MW
3.9 YRS
Rutland Garden Centre, Ashwell Road - Solar 0 MW
3.3 YRS
Mallard Pass Solar Farm 350 MW
2.1 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Mallard Pass Solar FarmSolar Photovoltaics127,000 homes350.0 MW2024-072.1 yrs
Ranksborough FarmSolar Photovoltaics10,000 homes28.0 MW2022-014.5 yrs
Morrison - Roof mounted solar panelsSolar Photovoltaics200 homes0.7 MW2022-064.2 yrs
Openfield, Colsterworth - Solar PV SystemSolar Photovoltaics100 homes0.4 MW2022-084.0 yrs
Rutland Garden Centre, Ashwell Road - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-043.3 yrs
Cherryholt Road - Solar PanelsSolar Photovoltaics100 homes0.2 MW2022-083.9 yrs

Plus 5 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Alicia Kearns said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)